CALCULATING BLOOPER S PROJECT CASH FLOWS
Table 4.3 provides all the
information you need to figure out the cash flows on the magnoosium project. In Table 4.4 we use this information to
set out the project cash flows. Capital Investment. Investment in plant and
equipment is taken from line 1 of Table 4.3. Blooper s initial investment is a negative
cash flow of $10 million.
Investment in Working Capital. We ve seen that investment in working capital, just like investment in plant
and equipment, produces a negative cash
flow. Disinvestment in
working capital produces a positive cash flow. The numbers required for these
calculations come
from lines 2 and 3 of Table 4.3. Line 3 shows the increase in
working capital.
Therefore, the cash flow associated with investments in working capital is simply the negative of line 3.
Cash Flow from Operations. The necessary data for these calculations come from lines 4 9 of Table 4.3.
We ve seen that there are at least three ways to compute these cash flows (using any of methods 1, 2, or 3). For
example, using the net profit + depreciation approach, the first- year cash flow from operations (in thousands) is profit after tax +
depreciation expense = 1,950 + 2,000 = 3,950 or $3,950,000. You can apply the same calculation to the other years to obtain line 3 of Table 4.3.
CALCULATING THE NPV OF BLOOPER S PROJECT
You have now derived (in the last line of Table 4.4)
the forecast cash flows from Blooper s magnoosium mine. Assume that investors
expect a return of 12 percent from investments in the capital market with the same risk
as the magnoosium project. This is the opportunity cost of the shareholders money that Blooper is proposing to invest in the project. Therefore, to
calculate NPV you need to discount the cash flows at 12 percent. Table 4.5 sets out the calculations. Remember that to
calculate the present value of a cash flow in Year t you
can divide the cash flow by (1 + r)t or
you can multiply by a discount
factor which is equal to 1/(1 + r)t.
When all cash flows are discounted and added up, the magnoosium project is seen to offer a
positive net present value of almost $3.6 million.
Now here is a small point that often causes confusion.
To calculate the present value of the first year s cash flow, we divide by (1 + r)
= 1.12. Strictly speaking, this makes sense only if all the sales and all the costs occur
exactly 365 days, zero hours, and zero minutes from now. But of course the year s sales don t all take place on the stroke of midnight on December 31.
However, when making capital budgeting decisions, companies are
usually happy to pretend that all cash flows occur at 1-year intervals. They pretend this for one
reason only simplicity. When sales forecasts
are sometimes little more
than intelligent guesses, it may be pointless to inquire how the sales are
likely to be
spread out during the year.5
A
Spreadsheet Model for Blooper
You might have guessed that discounted cash-flow
analysis such as that of the Blooper case is tailor-made for spreadsheets.
The worksheet directly above shows the
formulas from the Excel spreadsheet that we used to generate the Blooper
example. The spreadsheet on the facing page shows the resulting values, which appear
in the text in Tables 4.3 through 4.5.
The assumed values are the capital investment (cell
B2), the initial level of revenues (cell C5), and expenses (cell C6). Rows 5
and 6 show that each entry for revenues
and expenses equals the previous value times (1 + inflation rate), or 1.05. Row
3, which is the amount of working
capital, is the sum of inventories and accounts receivable. To capture the fact
that inventories tend to rise with
production, we set working capital equal to .15 times the following
year s expenses. Similarly, accounts receivables rise with sales, so we assumed that accounts receivable
would be 1/6 times the current year s revenues. Each entry in row 3 is the sum
of these two quantities.1 Net
investment in working capital (row 4)
is the increase in working capital from one year to the next.
Cash flow (row 12) is capital investment plus change
in working capital plus profit after tax plus depreciation. In row 13 we
discount cash flow at a 12 percent
discount rate and in cell B14 we add the present value of each cash flow to
find project NPV. Once the spreadsheet
is up and running it is easy to do various sorts of what if analysis. Here
are a few questions to try your hand.
Questions
1. What happens to cash
flow in each year and the NPV of the project if the firm uses MACRS depreciation assuming a 3-year recovery period? Assume that Year 1 is the
first year that depreciation is taken.
2. Suppose the firm can
economize on working capital by managing inventories more efficiently. If the firm can reduce inventories from 15 percent to 10 percent of
next year s cost of goods sold, what will be
the effect on project NPV?
Category: Cash flows
|