OTHER PITFALLS OF THE IRR RULE
The IRR rule is subject to
problems beyond those associated with mutually exclusive investments. Here are
a few more pitfalls to avoid. Pitfall 2:
Lending or Borrowing? Remember
our condition for the IRR rule to work: the project s NPV must fall as the
discount rate increases. Now consider
the following projects:
Each project has an IRR of 50 percent. In other words,
if you discount the cash flows at 50 percent, both of them would have zero
NPV. Does this mean that the two projects are equally attractive? Clearly
not. In the case of J we are paying out $100 now and getting $150 back at the
end of the year. That is better than
any bank account. But what about K? Here we are getting paid $100 now but we
have to pay out $150 at the end of the
year. That is equivalent to borrowing money at 50 percent.
If someone asked you whether 50 percent was a good
rate of interest, you could not answer unless you also knew whether that person
was proposing to lend or borrow at that
rate. Lending money at 50 percent is great (as long as the borrower does not
flee the country), but borrowing at 50
percent is not usually a good deal (unless of course you plan to flee the
country). When you lend money, you want a high rate of return; when you borrow, you want a low rate
of return. If you plot a graph like Figure 4.2 for project K, you will find the
NPV increases as the discount rate
increases. (Try it!) Obviously, the rate of return rule will not work in
this case.
Project K is a fairly obvious trap, but if you want to
make sure you don t fall into it, calculate the project s NPV. For example,
suppose that the cost of capital is 10
percent. Then the NPV of project J is + $36.4 and the NPV of project K is
$36.4. The NPV rule correctly warns us away
from a project that is equivalent to borrowing money at 50 percent. When
NPV rises as the interest rate rises, the rate of return rule is reversed:
When NPV is higher as the discount rate increases, a
project is acceptable only if its internal rate of return is less than the opportunity cost of capital.
Pitfall 3: Multiple Rates of Return. Here is a trickier problem. King Coal Corporation is
considering a project to strip mine coal. The project requires an investment of $22 million and is expected to produce
a cash inflow of $15 million in each of Years 1 through 4. However, the company is obliged in Year 5 to reclaim the
land at a cost of $40 million. At a 10 percent opportunity cost of capital the
project has an NPV of $.7 million. To
find the IRR, we have calculated the NPV for various discount rates and plotted
the results in Figure 4.5. You can see that there are two discount rates at which NPV = 0. That is, each of the following statements holds:
In other words, the investment has an IRR of both 6 and 28
percent. The reason for this is the double change in the sign of the cash
flows. There can be as many different
internal rates of return as there are changes in the sign of the cash-flow
stream.8 Is the coal mine worth developing? The simple IRR rule accept if the IRR is greater
than the cost of capital won t help. For example, you can see from Figure 4.5
that with a low cost of capital (less
than 6 percent) the project has a negative NPV. It has a positive NPV only if
the cost of capital is between 6 percent and 28 percent.
When there are multiple changes in the sign of the
cash flows, the IRR rule does not work. But the NPV rule always does.
Category: Cash flows
|