REPLACING AN OLD MACHINE
The previous example took
the life of each machine as fixed. In practice, the point at which equipment is
replaced reflects economics, not
physical collapse. We usually decide when to replace. The machine will
rarely decide for us.
Here is a common problem.
You are operating an old machine that will last 2 more years before it gives up
the ghost. It costs $12,000 per year to
operate. You can replace it now with a new machine, which costs $25,000
but is much more efficient ($8,000 per year in operating costs) and will last for 5 years. Should you replace it
now or wait a year? The opportunity cost of capital is 6 percent. We can
calculate the NPV of the new machine
and its equivalent annual cost, that is, the 5-year annuity that has the same
present value.
The cash flows of the new machine are equivalent to an
annuity of $13,930 per year. So we can equally well ask at what point we would
want to replace our old machine, which
costs $12,000 a year to run, with a new one costing $13,930 a year. When the
question is posed this way, the answer
is obvious. As long as your old machine costs only $12,000 a year, why replace
it with a new machine that costs $1,930 more?
MUTUALLY EXCLUSIVE PROJECTS AND THE IRR RULE
Whereas the NPV rule deals
easily with mutually exclusive projects, the IRR rule does not. Because of the
potential pitfalls in the use of the IRR
rule, our advice is always to base your final decision on the project s
net present value.7
Pitfall 1: Mutually Exclusive Projects. We have seen that firms are seldom faced with
take-it-or-leave-it projects. Usually they need to choose from a number of mutually exclusive
alternatives. Given a choice between competing projects, you should accept the
one that adds most to shareholder
wealth. This is the one with the higher NPV. However, it won t necessarily be
the project with the higher internal rate of return. So the IRR rule can lead
you astray when choosing between projects.
Think once more about the two office-block proposals. You initially
intended to invest $350,000 in the
building and then sell it at the end of the year for $400,000. Under the
revised proposal, you planned to rent out the
offices for 3 years at a fixed annual rent of $16,000 and then sell the
building for $450,000. Here are the cash flows, their IRRs, and their NPVs:
Both projects are good investments; both offer a
positive NPV. But the revised proposal has the higher net present value and
therefore is the better choice. Unfortunately,
the superiority of the revised proposal doesn t show up as a higher rate of
return. The IRR rule seems to say you
should go for the initial proposal because it has the higher IRR. If you
follow the IRR rule, you have the satisfaction of earning a 14.29 percent rate of return; if you use NPV, you are
$59,000 richer.
Figure 4.4 shows why the IRR rule gives the wrong
signal. The figure plots the NPV of each project as a function of the discount
rate. These two NPV profiles cross at
an interest rate of 12.26 percent. So if the opportunity cost of capital is
higher than 12.26 percent, the initial proposal, with its rapid cash inflow, is the superior investment. If the cost of
capital is lower than 12.26 percent, then the revised proposal dominates. Depending on the discount rate, either
proposal may be superior. For the 7 percent cost of capital that we have
assumed, the revised proposal is the
better choice. Now consider the IRR of each proposal. The IRR is simply the
discount rate at which NPV equals zero, that is, the discount rate at which the NPV profile crosses the
horizontal axis in Figure 4.4. As noted, these rates are 14.29 percent for the
initial proposal and 12.96 percent for
the revised proposal. However, as you can see from Figure 4.4, the higher IRR
for the initial proposal does not mean that it has a higher NPV. In our example both projects involved the same
outlay, but the revised proposal had the longer life. The IRR rule mistakenly favored the quick payback project with the
high percentage return but the lower NPV.
Remember, a high IRR is not an end in itself.You want
projects that increase the value of the firm. Projects that earn a good rate
of return for a long time often have higher NPVs than those that offer
high percentage rates of returnbut die young.
Pitfall 1a: Mutually Exclusive Projects Involving
Different Outlays. A
similar misranking also may occur when comparing projects with the same lives but different outlays. In this
case the IRR may mistakenly favor small projects with high rates of return but
low NPVs.
Category: Cash flows
|