Valuing a New Computer System
Obsolete Technologies is considering the purchase of a
new computer system to help handle its warehouse inventories. The system
costs $50,000, is expected to last 4
years, and should reduce the cost of managing inventories by $22,000 a year.
The opportunity cost of capital is 10 percent. Should Obsolete go ahead?
Don t be put off by the fact that the computer system
does not generate any sales. If the expected cost savings are realized, the
company s cash flows will be $22,000 a
year higher as a result of buying the computer. Thus we can say that the
computer increases cash flows by $22,000 a year for each of 4 years. To calculate present value, you can discount
each of these cash flows by 10 percent. However, it is smarter to recognize
that the cash flows are level and
therefore you can use the annuity formula to calculate the present value:
The net present value is NPV = $50,000 + $69,740 =
$19,740 The project has a positive NPV of $19,740. Undertaking it would
increase the value of the firm by that
amount.
The first two steps in calculating NPVs forecasting
the cash flows and estimating the opportunity cost of capital are tricky, and
we will have a lot more to say about
them in later material. But once you have assembled the data, the calculation
of present value and net present value
should be routine. Here is another example.
Calculating Eurotunnel s NPV
One of the world s largest commercial investment
projects was construction of the Channel Tunnel by the Anglo-French company
Eurotunnel. Here is a chance to put
yourself in the shoes of Eurotunnel s financial manager and find out whether
the project looked like a good deal for
shareholders. The figures in the column headed cash flow in Table 4.1 are based on the forecasts of
construction costs and revenues that the company provided to investors in 1986.
The Channel Tunnel project was not a safe investment.
Indeed the prospectus to the Channel Tunnel share issue cautioned investors
that the project involves significant
risk and should be regarded at this stage as speculative. If for any reason the
Project is abandoned or Eurotunnel is
unable to raise the necessary finance, it is likely that equity
investors will lose some or all of their money.
To induce them to invest in the project, investors
needed a higher prospective rate of return than they could get on safe
government bonds. Suppose investors
expected a return of 13 percent from investments in the capital market that had
a degree of risk similar to that of the Channel Tunnel. That was what investors were giving up when they provided
the capital for the tunnel. To find the project s NPV we therefore
discount the cash flows in Table 4.1 at
13 percent.
Since the tunnel was expected to take about 7 years to
build, there are 7 years of negative cash flows in Table 4.1. To calculate NPV
you just discount all the cash flows,
positive and negative, at 13 percent and sum the results. Call 1986 Year 0,
call 1987 Year 1, and so on. Then Net
present value of the forecast cash flows is АВАі251 million, making
the tunnel a worthwhile project, though not by a wide margin, considering the
planned investment of nearly АВАі4 billion.
Of course, NPV calculations are only as good as the
underlying cash-flow forecasts. The well-known Pentagon Law of Large Projects
states that anything big takes longer
and costs more than you re originally led to believe. As the law predicted, the
tunnel proved much more expensive to
build than anticipated in 1986, and the opening was delayed by more than
a year. Revenues also have been below forecast, and Eurotunnel has not even generated enough profits to pay the
interest on its debt. Thus with hindsight, the tunnel was a negative-NPV
venture.
Note: Cash flow for 2010 includes the value in 2010 of forecast cash flows in
all subsequent years. Source: Eurotunnel Equity II Prospectus,
October 1986. Used by permission. Some of these figures involve
guesswork because the prospectus reported
accumulated construction costs
including interest expenses.
Category: Cash flows
|