the normal level of sales
Break-even analysis finds the level of sales or revenue at which NPV =
0. Sensitivity analysis changes these and other input variables to optimistic and pessimistic values and
recalculates NPV.
5 Reworking Table 8.6 for the normal level of sales
and 10 percent higher sales gives the following: For the high-fixed-cost
policy, profits increase by 54.5
percent, from $550,000 to $850,000. For the low-fixed-cost policy, profits
increase by 46.5 percent. In both cases
the percentage increase in profits equals DOL times the percentage
increase in sales. This illustrates that DOL measures the sensitivity of profits to changes in sales.
6 The option to shut down is valuable because the mine operator can avoid
incurring losses when copper prices are low. If the shut-down option were not available, cash flow in the
lowprice periods would be negative. With the option, the worst cash flow is
zero. By allowing managers to respond
to market conditions, the option makes the worst-case cash flow better than it
would be otherwise. The average cash
flow (that is, averaging over all possible scenarios) therefore must
improve, which increases project NPV.
7 Abandonment options, options due to flexible
production facilities, investment timing options.
Maxine Peru, the CEO of Peru Resources, hardly noticed the plate of
savory quenelles de brochet and the glass of Corton Charlemagne `94 on the
table before her. She was absorbed by the engineering report handed to her just
as she entered the executive dining room.
The report described a proposed new mine on the North Ridge of Mt.
Zircon. A vein of transcendental zirconium ore had been discovered there on land owned by Ms. Peru`s
company. Test borings indicated sufficient reserves to produce 340 tons per
year of transcendental zirconium over a
7-year period.
The vein probably also contained hydrated zircon gemstones. The amount
and quality of these zircons were hard to predict, since they tended to occur in БІАААмpockets.БІАААн The new mine
might come across one, two, or dozens of pockets. The mining engineer guessed
that 150 pounds per year might be
found. The current price for high-quality hydrated zircon gemstones was $3,300
per pound.
Peru Resources was a family-owned business with total assets of $45
million, including cash reserves of $4 million. The outlay required
for the new mine would be a major commitment. Fortunately, Peru Resources
was conservatively financed, and Ms. Peru believed that the company could borrow up to $9 million at
an interest rate of about 8 percent.
The mine`s operating costs were projected at $900,000 per year,
including $400,000 of fixed costs and $500,000 of variable costs. Ms. Peru thought these forecasts were accurate.
The big question marks seemed to be the initial cost of the mine and the
selling price of transcendental zirconium.
Opening the mine, and providing the necessary machinery and
ore-crunching facilities, was supposed to cost $10 million, but cost overruns of 10 percent or 15 percent were
common in the mining business. In addition, new environmental regulations, if
enacted, could increase the cost of the
mine by $1.5 million. There was a cheaper design for the mine, which would
reduce its cost by $1.7 million and
eliminate much of the uncertainty about cost overruns. Unfortunately,
this design would require much higher fixed operating costs. Fixed costs would increase to $850,000 per year at
planned production levels.
The current price of transcendental zirconium was $10,000 per ton, but
there was no consensus about future prices.1
Some experts were
projecting rapid price increases to as much as $14,000 per ton. On the
other hand, there were pessimists saying that prices could be as low as $7,500 per ton. Ms. Peru did not have
strong views either way: her best guess was that price would just increase with
inflation at about 3.5 percent per
year. (Mine operating costs would also increase with inflation.)
Ms. Peru had wide experience in the mining business, and she knew that
investors in similar projects usually wanted a forecasted nominal rate of return of at least 14
percent.
You have been asked to assist Ms. Peru in evaluating this project. Lay
out the base-case NPV analysis and undertake sensitivity, scenario, or break-even analyses as appropriate.
Assume that Peru Resources pays tax at a 35 percent rate. For simplicity, also
assume that the investment in the mine
could be depreciated for tax purposes straight-line over 7 years.
What forecasts or scenarios should worry Ms. Peru the most? Where would
additional information be most helpful? Is there a case for delaying
construction of the new mine?
Category: Capital management
|